The building going up behind the new construction signage in Carlton Landing is called the Nature Center. The town's Summer 2025 community magazine describes classrooms, exhibit areas, a full kitchen, gathering spaces for large and small events, and the Town's administrative offices, all inside the first phase of a new Town Center. Crews broke ground on Friday, September 18, 2026. The money comes through the Carlton Landing Economic Development Trust, which borrows against the growth in the town's own property tax base.
So this is the town's first true indoor public room. It's being built for weather, and it's financed by the town's own growth. Everything happening at the site this fall follows from those two facts.
A nature center with a kitchen and the town offices
Carlton Landing already has a nature area. The town's Parks & Pools page describes the Nature Center as exhibits, miles of walking trails and an outdoor playground. Through a partnership with The Nature Conservancy, it also serves as outdoor learning space for students at Carlton Landing Academy, residents and guests. Nearby, The Trailway runs five miles of gravel trail along the Lake Eufaula shore, with a natural playground and a creek bridge just off the path. Everything on that list happens outdoors.
The new building adds a roof over it all. Sommer Design Studios designed it, and the plan in the Summer 2025 issue of the town's community magazine calls for spaces that can host both large and small events, along with a full kitchen and the offices that run the town. In that same issue, Mayor Mary Myrick said the facility would provide:
"weather protection for our major events" and "effectively extend the season of activity for our community."
That's the reason for the building. Carlton Landing's calendar is built around the outdoors: the green, the boardwalk, the trail. Every event on it depends on the forecast. A kitchen and an event hall on the town's own land let a gathering go forward in rain or cold. The magazine also places the project inside the community master plan and the town's agreement with the U.S. Army Corps of Engineers.
The magazine treats the Nature Center as a first step. Plans for the surrounding Town Center, it says, "could one day include a chapel, lodge, shops, restaurants, and more." The slab now being prepared is the anchor those future buildings would sit around.
Where the crew stands as November begins
The town's meeting records give a fairly detailed picture of the work since groundbreaking. Thompson Construction is the builder. At the trust's September meeting, held the day after groundbreaking, Brian Kizzia and Adam Bales of Thompson gave the update.
- Friday, September 18. Groundbreaking on site.
- The trust's September meeting. Thompson reported the project on schedule. Crews had dug out a lot of rock, rebar was expected the following week, and the slab was projected for October 16, with vertical framing to follow. The trust also voted unanimously to approve Guaranteed Maximum Price #2 on the Nature Center Complex contract, at $1,679,515.
- Saturday, October 17. Town Administrator Greg Buckley's report said site work was moving forward, plumbing had started, and the contractor was still removing excess rock. Steel was due the following week, with footings to begin once it arrived.
By the mid-October report, then, the slab date had passed with the footings not yet started, and the rock was taking longer than the September forecast assumed. Builders on this shoreline tend to find the same thing once they start digging.
Thompson also told the trust in September that it had rebid some items to bring costs down. Earlier, at an August 15 meeting, staff reported that the combined Nature Center and Town Center work was running about $87,000 over an $8,000,000 target. The rebidding was aimed at that gap.
How a small lake town pays for an $8 million build
Carlton Landing doesn't pay for this out of a general fund the way a larger city might. The work runs through the Carlton Landing Economic Development Trust, known locally as CLEDT. CLEDT uses tax increment financing, which means it borrows against the property tax revenue that new growth adds to the town's base. The trust's FY 2026–27 budget, published in its October 17 meeting packet, shows the two lines that fund this project:
| Budget line | Budgeted | Spent year to date |
|---|---|---|
| 2021 Rev Note, Nature Center | $6,500,000 | $55,260 |
| Rev Note, Town Center Infrastructure | $1,400,000 | $214,489 |
The two lines are moving at different speeds. Year-to-date spending on the Nature Center comes to 0.9 percent of its budget, while the Town Center infrastructure line stands at 15.3 percent, with $114,818 of it recorded in the latest month alone. That order matches the work on the ground. The waterlines and drainage under the Town Square went in first, and a building still at the rock-and-plumbing stage hasn't drawn much of its money yet.
In September, the trust and the Board of Trustees also approved a new Tax Increment Revenue Note, Taxable Series 2026, for up to $2,700,000, secured by a pledge of ad valorem tax increment revenue. According to the minutes, Chris Gander presented the note's financials and explained that it would give the TIF better cash flow for other projects while the Nature Center is underway. Buckley's October report said the town asked MidFirst, Firstar and Gateway banks for quotes. Firstar offered a 7.0 percent fixed rate on a 10-year term with no origination fee, and the town planned to close the note with Firstar by October 30.
The Board of Trustees' September minutes add one more piece. Buckley reported that the July/August report showed the town's highest sales tax and lodging tax revenue yet, and that a service called Rentalscape is helping with collections. A town whose busiest months set revenue records is now building a room meant to make the quieter months busier.
The rest of this fall's construction
The Nature Center is the biggest project in the October packets, but it isn't the only one. Several of the others prepare the ground the Town Center will need.
- Town Square infrastructure. Maas Bach reported in September that waterlines were about a week out. After a small drainage redesign, the work was expected to wrap up by mid-November.
- Water to the marina. The trust asked the Town Developer for a bill covering a waterline to the marina, with the goal of having water there by next season.
- Alleys and new phases. Alleys in Phases 5A and 6 were reported complete, with some spots needing more repair. Phase 5B was expected to finish by mid-October. Kiamichi Electric had run electrical lines in Phase 8, with paving, sidewalks and landscaping scheduled to begin the first week of October. At The Homestead, trees were being cleared and the land surveyed.
- Stephens Road. Freese and Nichols is reviewing the scope of the remaining work. The surety has offered to bring the road to a chip-seal finish, and it has chosen HD Dirt Works to do the work once a notice to proceed is issued. Attorneys are drafting a supplemental agreement for the trustees to approve.
Put together, the Town Square utilities, the marina waterline and the Nature Center slab are one coordinated push to build the core of a town center around the green.
Watching it go up
At the September meeting, the mayor asked that signage go up at the Town Center and Nature Center sites as soon as possible. Buckley's October report said work on the Nature Center project sign was underway. In the 2025 magazine, Myrick said she hoped residents would "regularly swing by and take a look at the progress over the coming two years."
Anyone who wants to follow the work in more detail than a site visit allows can find it in the town's public documents page, which posts each meeting's agenda and packet. The town notes that these posted copies are unofficial and that official records are kept by the Town Clerk. The October 17 packets have the latest construction reports. The next ones should show whether the steel arrived and the footings were poured.
Katie Chapman has lived in Carlton Landing since 2014 and has watched the town fill in one park and one street at a time. If you'd like to talk about how the Town Center plans relate to the part of town you own in or are thinking about, Carlton Landing Homes is glad to walk the site with you and share what we know.